Henderson Intermediate School

Project Requirements

Total Tonnage – 165 T

Challenges

8 x Seismic cranked frames through the core of the building meant that fabrication tolerances had to be extremely accurate. Multiple Different paint systems were required on the project so we had to ensure this was coordinated through the workshop and paint shop accurately and effectively. Due to the volume of steel in a small area, our job sequencing and load stacking onsite had to be thought out and coordinated to ensure this didn’t effect other trades.